05. INSTALLATION
Protected on-site installation, clear progress, and the 45% milestone before benchtop installation.

Our On-Site Standards
Installation is not only about fitting cabinets. It is also about how we protect your home and work around your daily life.
A Typical Installation Timeline
A simple view of how installation, templating, benchtop production, and final completion usually move on site.
Day 1
Site Protection
& Installation Start
Site protection is laid down and cabinet installation begins.
Day 2
Cabinet Installation
& Benchtop Templating
Cabinet installation continues, followed by benchtop templating.
Milestone Payment: The 45% progress payment becomes due once cabinet installation is completed.
Day 3–7
Benchtop Production Period
Benchtop production usually takes 3–5 working days.
Any remaining installation details may also be completed during this period.
Day 8
Benchtop Installation & Final Check
Benchtop installation, protection removal, and final site cleaning and check.
Final Balance: The remaining 5% balance becomes due after final completion.
Note: Actual timing may vary depending on site conditions, coordination, and supplier scheduling.
Note: Actual timing may vary depending on site conditions, coordination, and supplier scheduling.